
SOUTH TULSA ROAD PROJECTS
Stay up to date on road work projects throughout South Tulsa!
• Project Update as of: October 13, 2023
• Project Scope: Five lane with bike lanes and sidewalks on both sides of road
• Start Date: July 6, 2021
• Projected Completion Date: October 2023
• Funding Details: Improve Our Tulsa ($13,893,780)
August 25, 2022 Video Update:
%20(7).png)
-
Project Update as of: August 19, 2024
-
Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls
-
Start Date: November 15, 2021
-
Projected Completion Date: August 19 2024
-
Funding Details: Improve Our Tulsa ($29,257,000)
View the widening construction schedule here
Watch the Town Hall to discuss all aspect of this project here

• Project Update as of: May 5, 2025
• Project Scope: Five lane with bike lanes and sidewalks on both sides of street
-
Funding Sources: Vision Tulsa, Water Enterprise, Stormwater Enterprise, Improve Our Tulsa, and completed street projects.
-
Consultant: Garver
-
Consultant Design Status: Complete. Contract approved.
-
R/W Status: Complete: 14 of 20 parcels have been closed. Six removed. ROW complete.
-
Utility Status: Windstream is complete.
-
Contractor: Tri-Star Construction
-
Construction Cost Estimate: $12,800,000.00
-
Construction Start: Advertisement for bids scheduled for June 2024. Funding options being reviewed.
-
Construction Completion: Estimated January 21, 2027
-
Traffic Control:
-
Brief flagging as needed.
-
-
Construction Activities:
-
Public Meeting: January 16, 2025, at Hardesty Regional Library (8316 E 93rd Street) at 6:00 p.m.
-
Channel work is ongoing.
-
Roadway subgrade and aggregate base is ongoing.
-
Placement of concrete paving is ongoing.
-
Stormwater work is ongoing.
-
Stormwater work is ongoing.
-
RCB installed in Phase 1 is complete and concrete crews working on extensions and headwalls.
-
Waterline crews working on church fire service line, services to churches and tie-ins to neighborhoods on South side of 91st.
-
.jpg)
-
Project Update as of: May 5, 2025
-
Project Scope: Widened concrete intersection with sidewalks
-
Funding Sources: Improve Our Tulsa
-
Construction Cost Estimate: $12,000,000
-
Construction Start : Construction funding is anticipated FY27
-
Construction Completion: TBD
-
Traffic Control:
-
N/A
-
-
Construction Activity:
-
N/A
-
• Project Update as of: February 14, 2022
• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades
• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)
%20(7).png)
• Project Update as of: March 15, 2022
• Project Scope: Concrete patching
• Start Date: April 15, 2021
• Projected Completion Date: February 2022
• Funding Details: Improve Our Tulsa ($2,228,000)
%20(7).png)
• Project Update as of: August 22, 2022
• Project Details: Five lane with sidewalks on both sides of the road
• Start Date: August 19, 2019
• Projected Completion Date: July 2022
• Funding Details: Vision Tulsa ($7,430,588.70)
%20(7).png)
• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay
• Funding Details: Improve Our Tulsa ($1,414,641)
%20(7).png)
• Project Update as of: February 14, 2022
• Project Scope: Concrete patching
• Start Date: February 15, 2021
• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)
%20(7).png)
• Project Update as of: December 7, 2021
• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road.
• Funding Details: Improve Our Tulsa ($8,752,795)
%20(7).png)
-
Project Update as of: May 5, 2025
-
Project Scope: Arterial street rehabilitation, stormwater improvements, sidewalks, and waterline replacement.
-
Funding Details:
-
Improve Our Tulsa - $2,840,000
-
Vision School Safety First - $542,000
-
Stormwater - $501,000
-
Water Enterprise Funding - $610,000
-
-
Design
-
Design Consultant: CEC - Consulting Engineers
-
Design Status: Ongoing
-
Advertising scheduled June 2025
-
36" waterline is not currently available. Construction start in the fall allows for pipe procurement and seasonal restrictions.
-
Drainage is being reviewed at east end on south side.
-
-
Construction Cost Estimate: TBD
-
Construction Start: End of Summer 2025
-
Construction Completion: TBD
-
Traffic Control:
-
Road closure in Summer 2026
-
-
Construction Activities:
-
N/A
-
-
Project Update as of: April 15, 2025
-
Project Scope: Patching, milling, and overlaying the existing roadway with asphalt. Extending and connecting sidewalks. Fixing the pedestrian/bicycle crossing at the Creek.
-
Funding Sources: Improve Our Tulsa 3
-
Construction Contractor: Tri-Star Construction, LLC
-
Construction Cost Estimate: $1.2 million
-
Construction Start: September 2024
-
Construction Completion: May 2025
-
Traffic Control:
-
TBD
-
-
Construction Activity:
-
TBD
-
Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of.
1) Memorial Drive, 71st to 81st
• Project Updated as of: September 11, 2024
• Project Scope: Raise stormwater curb inlets and aprons on the outside lanes of Memorial Drive. Remove and replace pavement near the improved inlets.
• Funding Details: Improve Our Tulsa 2 and Public Works ($250,000)

Memorial Drive & US-169 Interchange
• Project Update as of: October 9, 2024
Read more about this project on ODT's website here.
Project Improvements:
○ Add Traffic Control Devices
○ Add capacity to roadway
○ Intersection Modification
• Project Scope: The project will improve the U.S. 169 and Creek Turnpike interchange, constructing eastern Oklahoma's first diverging diamond interchange.
• Start Date: February 6, 2023
• Projected Completion Date: Spring 2024
• Funding Details: ODOT ($13,733,920)

101st and Garnett
There will be work done in this area that is done by the County, State and Federal entities. Please contact ODOT for more information:
Randle White, P.E.
District 8 Engineer
918-838-9933
For information on ODOT projects that may impact your commute, you can find map/construction information here.
Learn more about Tulsa County projects here.