SOUTH TULSA ROAD PROJECTS

Stay up to date on road work projects throughout South Tulsa!

plus sign

• Project Update as of: February 14, 2022

• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades

• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)

complete
plus sign

• Project Update as of: March 15, 2022

• Project Scope: Concrete patching

• Start Date: April 15, 2021

• Projected Completion Date: February 2022

• Funding Details: Improve Our Tulsa ($2,228,000)

complete
plus sign

• Project Update as of: August 22, 2022

• Project Details: Five lane with sidewalks on both sides of the road

• Start Date: August 19, 2019

• Projected Completion Date: July 2022

• Funding Details: Vision Tulsa ($7,430,588.70)

complete
plus sign

• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay

• Funding Details: Improve Our Tulsa ($1,414,641)

complete
plus sign

• Project Update as of: February 14, 2022

• Project Scope: Concrete patching

• Start Date: February 15, 2021

• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)

complete
plus sign

• Project Update as of: November 17, 2022
○ Traffic Control:  81st/Memorial traffic normalized. 2-way traffic in eastbound lanes.
○ Construction Activities:  Little Haikey Creek Bridge: Complete. Wall G1: PSO pole conflict (redesigned footing details distributed 10.21.22). Awaiting feedback from PSO, confirming they have reviewed and approved the revised detail.

• Project Scope: Five lane with bike lanes and sidewalks on both sides of road

• Start Date: July 6, 2021

• Projected Completion Date: September 2022

• Funding Details: Improve Our Tulsa ($13,893,780)

August 25, 2022 Video Update:

Untitled (500 × 150 px) (7).png
plus sign

• Project Update as of: November 17, 2022
○ Traffic Control:  Left turns allowed at intersections 81st Street & Yale and 91st Street & Yale. One lane open in each direction.

 

Yale Avenue complete closure 120 days starting 03.28.22. Re-open date of 07.27.22. Before and after total closure, maintain one lane open in each direction. TPD, TFD, EMSA, and Jenks Schools notified. Before and after total closure, maintain one lane open in each direction. TPD, TFD, EMSA, and Jenks Schools to be notified.


  ○ Construction Activities:

  • Phase 1: COMPLETE

o Waterline D, K and M tied-in.

  • Phase 2: UNDERWAY

o Wall A (Canyon Creek Entrance-South): 99% Complete-Stain treatment underway.

o Wall B (Canyon Creek Entrance-North): 99% Complete-Stain treatment underway.

o Wall C (Cate Property-North): 99% Complete-Stain treatment underway.

o Wall F 99% Complete-Stain treatment is pending.

o Wall M (Cate Property Driveway): 99% Complete-Stain treatment underway.

o Roadway:

o South Slope Permanent Pavement: Complete-now under traffic.

o North Slope Permanent Pavement: Backfill of Wall F approximately 90% complete.

o Temporary Pavement: South portion complete. North portion to be installed in November-2022.

o Stormwater: South slope system underway. North slope system underway.

o Waterline: B, F, M complete.

o PSO Power Pole Footings: Allowances approved, install underway.

  • Phase 3: Specific Areas Authorized for work.

o Wall G: Drilled shafts underway.

o Wall H: Existing wall demolished. Utility conflicts confirmed clear.

o Wall J Drilled shafts complete. Ex 16” WL conflict resolved. Shot-crete and coping underway. Revised detail to add secondary footing distributed.

o Wall K Clearing and grubbing complete.

o Wall N: In redesign, pending feedback from Southern Pointe HOA.

• Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls

• Start Date: November 15, 2021

• Projected Completion Date: Fall 2023

• Funding Details: Improve Our Tulsa ($29,257,000)

View the widening construction schedule here

Watch the Town Hall to discuss all aspect of this project here

View the PDF document of the Town Hall presentation here

Untitled (500 × 150 px) (8).png
plus sign

• Project Update as of: December 7, 2021

• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road. 

• Funding Details: Improve Our Tulsa ($8,752,795)

complete
plus sign

Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of. 

1) Yale Avenue, 101st St to 111th St

• Project Updated as of: August 24, 2021

• Project Scope: Microsurfacing and traffic striping

• Funding Details: Improve Our Tulsa ($688,478)

complete
plus sign

101st and Garnett: There will be work done in this area that is done by the County, State and Federal entities. This area's updates may be lighter but will be accounted for to the best of our knowledge on this page.

For information on ODOT projects that may impact your commute, you can find map/construction information here: https://oklahoma.gov/odot.html

Tulsa County also a number of projects separate from City of Tulsa construction. You can learn more about County projects here: https://www.tulsacounty.org/tulsacounty/dynamic.aspx?id=10380