top of page

SOUTH TULSA ROAD PROJECTS

Stay up to date on road work projects throughout South Tulsa!

• Project Update as of: October 13, 2023

• Project Scope: Five lane with bike lanes and sidewalks on both sides of road

• Start Date: July 6, 2021

• Projected Completion Date: October 2023

• Funding Details: Improve Our Tulsa ($13,893,780)

​

August 25, 2022 Video Update:

Untitled (500 × 150 px) (7).png

Project Update as of: February 19, 2024

 

Traffic Control:

  • Left turns allowed at intersections 81st Street & Yale and 91st Street & Yale.

  • One lane opened in each direction.

Construction Activities:

  • Regular meetings with contractor to work on advancing schedule delays.

Phase 1: COMPLETE

​Phase 2: COMPLETE (Minus wall staining, which is weather-dependent)

Phase 3: Work underway on east half of project.

  • Wall G: (Southern Pointe Entrance – 88th Pl.): Complete​

  • Wall H: (Southern Pointe – B/T Entrances at 88th to 87th): Drain line added to collect private drain lines. Complete​

  • Wall J: (Signal Hill Entrance to Southern Pointe Entrance): Complete​

  • Wall K: (VINTAGE Apartments to Signal Hill Entrance): Complete​

  • Wall L (Vintage Apartments): Complete​

  • Wall N: (Southern Pointe Entrance at 87th): Complete​

  • Stormwater:

    • 01.29.24: South Slope, North Slope and RCB at South End of Project- Complete.

  • Waterline A (16” Main):

    • 12.20.23: Complete

  • Roadway:

    • Roadway: Northbound Pavement Install. All three lanes complete up to St 48+00. Expected to reach 84th St. by end of week of 09.29.23. this will allow for the possibility of flipping traffic onto NB driving lanes, and beginning work on Phase 4 retaining walls D & C, near 85th St.

    • 09.28.23: Northbound paving nearing 84th St. entrance to Signal Hill – all three lanes.

    • 10.05.23: Northbound paving has reached 84th St. entrance to Signal Hill. Asphalt crossover has been installed. Preparations underway to divert traffic, starting 10.10.23, from southbound pavement to northbound pavement in order to allow access to work areas for Phase 4 on west side of Yale.

    • 10.11.23: Northbound paving complete, all three lanes, from 89th St. Asphalt crossover constructed at 84th St. and traffic has been diverted onto the new northbound pavement. Preparation of base continues north of 84th St. for concrete pavement.

    • 11.15.23: 84th Street Entrance to Signal Hill – demo complete; prepping for concrete.

    • 12.08.23: Completion of Phase 3 northbound pavement is now dependent upon completion of storm water on north slope.

    • 01.29.24: Contractor placing aggregate base for permanent northbound roadway, north of 84th St. Progress on curb and gutter has reached Vintage on Yale Apartment Driveway.

    • 02.14.24: All Phase 3 curb and gutter complete. Phase 3 northbound pavement estimated to be complete in 3 weeks.

  • Phase 4: Underway on west side of Yale Ave. as of 10.10.23

    • Wall C (Horse Ranch Drive to New 85th St. Entrance to Brookwood): First portion of wall constructed in Phase 2. Balance to be completed with Phase 4.

      • Footings complete. Wall Panels 60% complete.

      • 02.14.24: Wall panel 87% complete (6 remain).

    • Wall D (North of New 85th) St. Entrance to Brookwood): Will cross and close current 85th St. entrance to Brookwood.

      • 12.20.23: Shot-Crete and Facade Wall underway.

      • 02.14.24: Excavation, Shot-Crete, Facade and Coping complete. Screen Walls underway.

    • Roadway: Southbound pavement and medians to be constructed this phase.

      • ​11.02.23: Southbound pavement install underway – south terminus to 50’ north of 87th St. complete (all 3 lanes). Progress continues northward toward Cate Ranch driveway.

      • 02.14.24: At new 85th St. entrance to Brookwood Addition, work nearing completion on Waterline "H" (ready for testing, the tie-in) which will clear the way for roadway prep to begin.

    • Landscaping: To be constructed this phase.

      • 11.02.23: As landscape work gets closer, coordination meeting being scheduled with Landscape Architect.

      • 11.15.23: Landscape Coordination Meeting scheduled for 11.30.23.

      • 12.08.23: Internal Meeting held- Full Pre-Landscape Coordination Meeting to be held with Contractor- Agenda developed.

      • 12.20.23: Pre-Landscaping Installation Coordination Meeting Agenda distributed. Meeting was held 02.02.24.

      • 02.14.24: Landscape Irrigation Submittal approved. Irrigation installation work to begin at site of backflow preventer, near 8th St. (Signal Hill entrance)- work to progress in zones. Each zone will begin with irrigation system install and testing, then followed with plantings before moving on to the next zone.

​

• Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls

• Start Date: November 15, 2021

• Projected Completion Date: June 2024

• Funding Details: Improve Our Tulsa ($29,257,000)

​

View the widening construction schedule here

Watch the Town Hall to discuss all aspect of this project here

View the PDF document of the Town Hall presentation here

STCU Map.png

• Project Update as of: October 13, 2023

• Project Scope: Five lane with bike lanes and sidewalks on both sides of street

  • Funding Sources: Vision Tulsa, Water Enterprise, Stormwater Enterprise, Improve Our Tulsa, and completed street projects.

  • Construction Cost Estimate: $16,500,000 (2022 estimate)

  • Construction Start: Advertisement for bids scheduled for June 2024.

  • Construction Completion: TBD

  • Traffic Control:

    • N/A

  • Construction Activities:

    • N/A

  • Project Update as of: August 22, 2023

  • Project Scope: Widened concrete intersection with sidewalks

  • Funding Sources: Improve Our Tulsa

  • Construction Cost Estimate: $12,000,000

  • Construction Start : Construction funding is anticipated FY27

  • Construction Completion: TBD

  • Traffic Control:

    • N/A

  • Construction Activity:

    • N/A

• Project Update as of: February 14, 2022

• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades

• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)

complete

• Project Update as of: March 15, 2022

• Project Scope: Concrete patching

• Start Date: April 15, 2021

• Projected Completion Date: February 2022

• Funding Details: Improve Our Tulsa ($2,228,000)

complete

• Project Update as of: August 22, 2022

• Project Details: Five lane with sidewalks on both sides of the road

• Start Date: August 19, 2019

• Projected Completion Date: July 2022

• Funding Details: Vision Tulsa ($7,430,588.70)

complete

• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay

• Funding Details: Improve Our Tulsa ($1,414,641)

complete

• Project Update as of: February 14, 2022

• Project Scope: Concrete patching

• Start Date: February 15, 2021

• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)

complete

• Project Update as of: December 7, 2021

• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road. 

• Funding Details: Improve Our Tulsa ($8,752,795)

complete

Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of. 

1) Yale Avenue, 101st St to 111th St

• Project Updated as of: August 24, 2021

• Project Scope: Microsurfacing and traffic striping

• Funding Details: Improve Our Tulsa ($688,478)

complete

Memorial Drive & US-169 Interchange

• Project Update as of: October 13, 2023

Read more about this project on ODT's website here.

 

Project Improvements:

â—‹ Add Traffic Control Devices

â—‹ Add capacity to roadway

â—‹ Intersection Modification

Traffic Impacts:

â—‹ Phased construction used to maintain existing traffic

â—‹ Truck route detour

Traffic Control:

â—‹ North and southbound Memorial Drive will maintain two lanes in each direction between 93rd St. and 97th St. throughout the majority of the project, except for a brief period when northbound traffic will be narrowed to one lane under the US-169 bridge. No ramp closures are expected for either U.S. 169 or the Creek Turnpike during construction.

 

Drivers are urged to give full attention to the road throughout construction and be aware of shifting lanes and new traffic configurations as work progresses.

 

• Project Scope: The project will improve the U.S. 169 and Creek Turnpike interchange, constructing eastern Oklahoma's first diverging diamond interchange. 

• Start Date: February 6, 2023

• Projected Completion Date: Spring 2024

• Funding Details: ODOT ($13,733,920)

STCU Map (1).png

101st and Garnett

There will be work done in this area that is done by the County, State and Federal entities. Please contact ODOT for more information: 

​

Randle White, P.E.

District 8 Engineer

rwhite@odot.org

918-838-9933

​

For information on ODOT projects that may impact your commute, you can find map/construction information here.

​

Learn more about Tulsa County projects here.

bottom of page