
SOUTH TULSA ROAD PROJECTS
Stay up to date on road work projects throughout South Tulsa!
• Project Update as of: October 13, 2023
• Project Scope: Five lane with bike lanes and sidewalks on both sides of road
• Start Date: July 6, 2021
• Projected Completion Date: October 2023
• Funding Details: Improve Our Tulsa ($13,893,780)
August 25, 2022 Video Update:


-
Project Update as of: August 19, 2024
-
Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls
-
Start Date: November 15, 2021
-
Projected Completion Date: August 19 2024
-
Funding Details: Improve Our Tulsa ($29,257,000)


• Project Update as of: June 23, 2026
• Project Scope: Five lane with bike lanes and sidewalks on both sides of street
-
Funding Sources: Vision Tulsa, Water Enterprise, Stormwater Enterprise, Improve Our Tulsa, and completed street projects.
-
Consultant: Garver
-
Consultant Design Status: Complete. Contract approved.
-
R/W Status: Complete: 14 of 20 parcels have been closed. Six removed. ROW complete.
-
Utility Status: Windstream is complete.
-
Contractor: Tri-Star Construction
-
Construction Cost Estimate: $12,800,000.00
-
Construction Start: Advertisement for bids scheduled for June 2024. Funding options being reviewed.
-
Construction Completion: Estimated January 21, 2027
-
Traffic Control:
-
Two-way traffic on North side of roadway.
-
-
Construction Activities:
-
Tri-Star continues to perform paving operations, curb and gutter placement, and subgrade along 91st street.
-
Public Works Engineering June 22, 2026 Page 8 of 56
-
175 W. 2nd Street, 13th Floor • Tulsa, OK 74103 • Office: (918) 596.7355 www.cityoftulsa.org
-
• Traffic switched to the new westbound lanes. In addition, access from S. 85th E. Avenue (Oakleaf subdivision) and S. 89th E. Avenue (Woodland Glen 4th) is closed due to elevation changes on E. 91st Street.
-
• Entry walls for Woodland Glen at S. 89th E. Avenue and S. 92nd E Avenue have been removed due to construction conflicts and a version of the entry walls with approval from the Neighborhood Association will be reconstructed.
-
• Riprap and topsoil installed on Channel 2. Riprap in pond complete and topsoil installation ongoing. Sodding remains on Channel 2 and pond.
-
• 91st St. mainline paving complete except for S. 88th E Ave return. 80% of sidewalk, curb and gutter complete.
-
• 24” sanitary sewer line cradle complete in compensatory storage area.
-
.jpg)
-
Project Update as of: March 23, 2026
-
Project Scope: Widened concrete intersection with sidewalks
-
Funding Sources: Improve Our Tulsa
-
Construction Cost Estimate: $12,000,000
-
Construction Start : Spring 2027
-
Construction Completion: TBD
-
Traffic Control:
-
N/A
-
-
Construction Activity:
-
N/A
-
• Project Update as of: February 14, 2022
• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades
• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)
%20(7).png)
• Project Update as of: March 15, 2022
• Project Scope: Concrete patching
• Start Date: April 15, 2021
• Projected Completion Date: February 2022
• Funding Details: Improve Our Tulsa ($2,228,000)
%20(7).png)
• Project Update as of: August 22, 2022
• Project Details: Five lane with sidewalks on both sides of the road
• Start Date: August 19, 2019
• Projected Completion Date: July 2022
• Funding Details: Vision Tulsa ($7,430,588.70)
%20(7).png)
• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay
• Funding Details: Improve Our Tulsa ($1,414,641)
%20(7).png)
• Project Update as of: February 14, 2022
• Project Scope: Concrete patching
• Start Date: February 15, 2021
• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)
%20(7).png)
• Project Update as of: December 7, 2021
• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road.
• Funding Details: Improve Our Tulsa ($8,752,795)
%20(7).png)
-
Project Update as of: June 23, 2026
-
Project Scope: Arterial street rehabilitation, stormwater improvements, sidewalks, and waterline replacement.
-
Funding Details:
-
Improve Our Tulsa - $2,840,000
-
Vision School Safety First - $542,000
-
Stormwater - $501,000
-
Water Enterprise Funding - $610,000
-
-
Design
-
Design Consultant: CEC - Consulting Engineers
-
Design Status: Ongoing
-
Advertising scheduled June 2025
-
36" waterline is not currently available. Construction start in the fall allows for pipe procurement and seasonal restrictions.
-
Drainage is being reviewed at east end on south side.
-
-
Construction Cost Estimate: $4,984,747.96
-
Construction Start: March 2026
-
Construction Completion: January 2027
-
Traffic Control:
-
Traffic control set up in Phase 1 at west bridge to begin waterline work.
-
-
Construction Activities:
-
Pre-construction meeting held 10.22.25 and 2.19.26
-
Meeting 03.31.26 to get plan for starting construction
-
PSO to relocate power pole at West Bridge.
-
Equipment and waterline delivered to site week of 4.20.26.
-
Summer Closure is in place.
-
12" and 36" waterline are ongoing.
-
.jpg)
-
Project Update as of: April 15, 2025
-
Project Scope: Patching, milling, and overlaying the existing roadway with asphalt. Extending and connecting sidewalks. Fixing the pedestrian/bicycle crossing at the Creek.
-
Funding Sources: Improve Our Tulsa 3
-
Construction Contractor: Tri-Star Construction, LLC
-
Construction Cost Estimate: $1.2 million
-
Construction Start: September 2024
-
Construction Completion: May 2025
-
Traffic Control:
-
TBD
-
-
Construction Activity:
-
TBD
-
Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of.
1) Memorial Drive, 71st to 81st
• Project Updated as of: September 11, 2024
• Project Scope: Raise stormwater curb inlets and aprons on the outside lanes of Memorial Drive. Remove and replace pavement near the improved inlets.
• Funding Details: Improve Our Tulsa 2 and Public Works ($250,000)

Garnett - 91st to 101st (County Project)
• Project Update as of: June 23, 2026
• Funding Details: Federal HMG Funds ($8.1M); County Funds ($1.7M)
• Project Scope:
○ Elevating & constructing the 101st & Garnett Rd intersection
○ Widen roadway & addition of turn lanes
○ Upgraded signalization for improved traffic flow
○ Tie-in’s to existing roadways to the west, south, and east legs
○ Elevation & construction of ~575 LF from intersection northward
• Impact:
○ Intersection closed completely during Phase 1
• Start Date: July/August, 2026 (Anticipated)
• Projected Completion Date: July/August 2027
• For questions, contact:
○ County Commissioner Kelly Dunkerley | 918-596-5010 | kdunkerley@tulsacounty.org
○ Chief Deputy Darren Gantz | 918-596-5510 | dgantz@tulsacounty.org
○ County Engineer Alex Mills | 918-596-5733 | amills@tulsacounty.org
• Traffic Control
○ N/A
• Construction Activities
○ The intersection of 101st and Garnett will be closed for three or four months during construction.
Memorial Drive & US-169 Interchange
• Project Update as of: October 9, 2024
Read more about this project on ODT's website here.
Project Improvements:
○ Add Traffic Control Devices
○ Add capacity to roadway
○ Intersection Modification
• Project Scope: The project will improve the U.S. 169 and Creek Turnpike interchange, constructing eastern Oklahoma's first diverging diamond interchange.
• Start Date: February 6, 2023
• Projected Completion Date: Spring 2024
• Funding Details: ODOT ($13,733,920)
Randle White, P.E.
District 8 Engineer
918-838-9933
For information on ODOT projects that may impact your commute, you can find map/construction information here.
Learn more about Tulsa County projects here.


.png)