top of page

SOUTH TULSA ROAD PROJECTS

Stay up to date on road work projects throughout South Tulsa!

• Project Update as of: October 13, 2023

• Project Scope: Five lane with bike lanes and sidewalks on both sides of road

• Start Date: July 6, 2021

• Projected Completion Date: October 2023

• Funding Details: Improve Our Tulsa ($13,893,780)

August 25, 2022 Video Update:

Untitled (500 × 150 px) (7).png
  • Project Update as of: August 19, 2024

  • Project Scope: Divided six lane with sidewalks on both sides of the road with fall protection walls

  • Start Date: November 15, 2021

  • Projected Completion Date: August 19 2024

  • Funding Details: Improve Our Tulsa ($29,257,000)

View the widening construction schedule here

Watch the Town Hall to discuss all aspect of this project here

View the PDF document of the Town Hall presentation here

2.jpg

• Project Update as of: May 5, 2025

• Project Scope: Five lane with bike lanes and sidewalks on both sides of street

  • Funding Sources: Vision Tulsa, Water Enterprise, Stormwater Enterprise, Improve Our Tulsa, and completed street projects.

  • Consultant: Garver

  • Consultant Design Status: Complete. Contract approved.

  • R/W Status: Complete: 14 of 20 parcels have been closed. Six removed. ROW complete. 

  • Utility Status: Windstream is complete.

  • Contractor: Tri-Star Construction

  • Construction Cost Estimate: $12,800,000.00

  • Construction Start: Advertisement for bids scheduled for June 2024. Funding options being reviewed.

  • Construction Completion: Estimated January 21, 2027

  • Traffic Control:

    • Brief flagging as needed.

  • Construction Activities:

    • Public Meeting: January 16, 2025, at Hardesty Regional Library (8316 E 93rd Street) at 6:00 p.m.

    • Channel work is ongoing.

    • Roadway subgrade and aggregate base is ongoing.

    • Placement of concrete paving is ongoing.

    • Stormwater work is ongoing.

    • Stormwater work is ongoing. 

    • RCB installed in Phase 1 is complete and concrete crews working on extensions and headwalls.

    • Waterline crews working on church fire service line, services to churches and tie-ins to neighborhoods on South side of 91st. 

STCU Map (12).jpg
  • Project Update as of: May 5, 2025

  • Project Scope: Widened concrete intersection with sidewalks

  • Funding Sources: Improve Our Tulsa

  • Construction Cost Estimate: $12,000,000

  • Construction Start : Construction funding is anticipated FY27

  • Construction Completion: TBD

  • Traffic Control:

    • N/A

  • Construction Activity:

    • N/A

• Project Update as of: February 14, 2022

• Project Scope: Replacement of waterlines, rehab concrete pavement, ADA sidewalk modifications and traffic signal upgrades

• Funding Details: STP Federal Funds and Improve Our Tulsa ($1,747,000)

complete

• Project Update as of: March 15, 2022

• Project Scope: Concrete patching

• Start Date: April 15, 2021

• Projected Completion Date: February 2022

• Funding Details: Improve Our Tulsa ($2,228,000)

complete

• Project Update as of: August 22, 2022

• Project Details: Five lane with sidewalks on both sides of the road

• Start Date: August 19, 2019

• Projected Completion Date: July 2022

• Funding Details: Vision Tulsa ($7,430,588.70)

complete

• Project Update as of: November 15, 2021
• Project Scope: Asphalt overlay

• Funding Details: Improve Our Tulsa ($1,414,641)

complete

• Project Update as of: February 14, 2022

• Project Scope: Concrete patching

• Start Date: February 15, 2021

• Funding Details: STP Federal Funds and Improve Our Tulsa ($2,987,000)

complete

• Project Update as of: December 7, 2021

• Project Scope: Improved intersection with turn bays, five lane with sidewalks on both sides of the road. 

• Funding Details: Improve Our Tulsa ($8,752,795)

complete
  • Project Update as of: May 5, 2025

  • Project Scope: Arterial street rehabilitation, stormwater improvements, sidewalks, and waterline replacement.

  • Funding Details: 

    • Improve Our Tulsa - $2,840,000​

    • Vision School Safety First - $542,000

    • Stormwater - $501,000

    • Water Enterprise Funding - $610,000

  • Design

    • Design Consultant: CEC - Consulting Engineers

    • Design Status: Ongoing

    • Advertising scheduled June 2025

    • 36" waterline is not currently available. Construction start in the fall allows for pipe procurement and seasonal restrictions. 

    • Drainage is being reviewed at east end on south side.

  • Construction Cost Estimate: TBD

  • Construction Start: End of Summer 2025

  • Construction Completion: TBD

  • Traffic Control:

    • Road closure in Summer 2026

  • Construction Activities:

    • N/A​

  • Project Update as of: April 15, 2025

  • Project Scope: Patching, milling, and overlaying the existing roadway with asphalt. Extending and connecting sidewalks. Fixing the pedestrian/bicycle crossing at the Creek.

  • Funding Sources: Improve Our Tulsa 3

  • Construction Contractor: Tri-Star Construction, LLC

  • Construction Cost Estimate: $1.2 million

  • Construction Start: September 2024

  • Construction Completion: May 2025

  • Traffic Control:

    • TBD​

  • Construction Activity:

    • TBD​

Sometimes there are minor projects that are slated to take a week or even days to complete that we still want to keep you aware of. 

1) Memorial Drive, 71st to 81st

• Project Updated as of: September 11, 2024

• Project Scope: Raise stormwater curb inlets and aprons on the outside lanes of Memorial Drive. Remove and replace pavement near the improved inlets.

• Funding Details: Improve Our Tulsa 2 and Public Works ($250,000)

Memorial Drive & US-169 Interchange

• Project Update as of: October 9, 2024

Read more about this project on ODT's website here.

Project Improvements:

○ Add Traffic Control Devices

○ Add capacity to roadway

○ Intersection Modification

• Project Scope: The project will improve the U.S. 169 and Creek Turnpike interchange, constructing eastern Oklahoma's first diverging diamond interchange. 

• Start Date: February 6, 2023

• Projected Completion Date: Spring 2024

• Funding Details: ODOT ($13,733,920)

2.jpg

101st and Garnett

There will be work done in this area that is done by the County, State and Federal entities. Please contact ODOT for more information: 

Randle White, P.E.

District 8 Engineer

rwhite@odot.org

918-838-9933

For information on ODOT projects that may impact your commute, you can find map/construction information here.

Learn more about Tulsa County projects here.

Was this page helpful?
Yes
No
Page selection

CONTACT

Who are you trying to contact?
  • Facebook
  • Instagram
  • X
  • Youtube
  • LinkedIn
  • Flickr
  • nextdoor final

*Information collected through the contact forms may be included in specific open records requests as described by the Oklahoma Open Records Act

bottom of page